Tuesday, 24 June 2014

24/06/2014

Work has now started on the solebar. As with A6071, work is starting low and in the dirty areas mainly due to the amount of work required. It is a slow progress, and we are still one short due to holidays. Work has started in the north east corner are will carry on along the east side. Once this side is complete, work will move under neath and behind, in areas you generally wont look, however like 6071 no area will go untouched.

In total 5 areas have been done, it took a while to clean this, swapping between a grinder and a drill to get into the corners. I am pleased with the outcome of the work and hopefully more can be completed tomorrow.

Below are photos of the area where work has started.